Short answer: Retrofit in this order: hazard map, route and 10-second walk, supply pressure measured flowing, drainage path, then equipment. Doing it in the reverse order - choosing the unit first - is what turns a two-week job into a two-month one.
Mark every point where a worker can be exposed, then draw the 10-second walking route from each to the proposed unit position. Retrofits fail here most often: the only free wall is 25 seconds away, or the direct route is blocked by a permanent rack.
If the route fails, the answer is a different position or a second unit - not a faster pump.
Older plants often have adequate static pressure and inadequate flowing pressure at the far end of a branch. Fit a gauge on the outlet, open the valve, and read it while water runs. If the figure is below the 30 psi requirement, the options are:
Re-pipe the branch in a larger diameter
Take the supply from a closer, larger main
Add a local booster with a fail-safe bypass
Substitute a gravity-fed portable unit where plumbing cannot be changed
A 15-minute flush is a lot of water. In an older building the nearest floor drain may be in another room, or the floor may fall the wrong way. Options in order of preference: existing floor drain, new trench drain to the nearest gully, a containment tray with a pump, or a location change.
Discharging onto a walkway is not an option - it converts a chemical hazard into a slip hazard at the exact moment someone is running to the unit.
| Constraint found | Practical answer |
|---|---|
| No free wall, supply nearby | Pedestal unit on a floor plate |
| Tight corridor, supply on the wall | Recessed or slim wall-mounted unit |
| No plumbing at all | Gravity-fed portable, with a refill owner |
| Outdoor or unheated | Heat-traced or heated-enclosure unit |
| Corrosive atmosphere | 316 stainless across the wet path |
| Low flowing pressure | Re-pipe or booster with bypass |
Record four numbers: flowing pressure at the outlet, flow rate, outlet temperature, and spray pattern height above the standing surface. Then assign the weekly activation to a named role and open the log. A retrofit without an owner reverts to non-compliance within a quarter.
For eyewash-only duty on a short branch, often yes - after measuring flowing pressure. Not for a combination shower.
Not always. A containment tray with a small transfer pump avoids excavation, at the cost of a maintenance item that must be on the inspection sheet.
Use a pedestal unit. A loaded wall-mounted unit plus a person leaning on it is a real load case, not a theoretical one.
The equipment installs in a day. The supply and drainage work sets the schedule, which is why they are measured first.